Posts in General News
Turntable Removal & Transportation Project

FMW Solutions LLC (FMW) was retained by Historic Watertown, Inc. (HWI) to manage the removal and transport of a 110 foot long turntable from Atlanta, Georgia, to Watertown, Tennessee. The turntable was graciously donated by CSX Transportation to HWI for preservation and installation in support of excursion trains operated by the Tennessee Central Railway Museum and, in the future, by the Nashville Steam Preservation Society.

With a very tight timeline, FMW collaborated with heavy lifting and transport firm Mammoet to undertake the move. FMW handled the railroad coordination, turntable disassembly, and overall project management, while Mammoet oversaw lifting and transport of the turntable. Working hand-in-hand, Mammoet and FMW disassembled, lifted, and transported the turntable and associated hardware from Atlanta to Watertown in just a few short weeks.

The turntable was delivered to Watertown in early January 2019, and its installation for use by the railroad and preservation groups is scheduled to take place in the coming years.

Turntable_small.jpg


Driving Wheel and Crankpin Machining Work for Steam Locomotive No. 1309

FMW Solutions LLC (FMW) was engaged by Diversified Rail Services to undertake specialized machining work on the six driving wheelsets of C&O steam locomotive No. 1309, a 2-6-6-2 locomotive built by the Baldwin Locomotive Works. The 1949-built Baldwin was recently acquired by the Western Maryland Scenic Railroad, and it is being returned to service as Western Maryland No. 1309 (WM 1309).

FMW was tasked with three main pieces of work: 1) re-profiling the axle journals: 2) re-profiling the wheel hubs; and 3) quartering the crankpins.

WM1309_2.jpg

To accomplish the re-profiling of the axle journal surfaces and the hub liners, FMW first worked with the Tennessee Valley Railroad Museum to return the journal lathe to like-new condition. Working off of an original set of drawings, FMW oversaw the repair to key hardware to return the machine to proper tolerance.

Once the journal lathe was repaired, FMW VP-Mechanical Shane Meador re-profiled all of the axle journal surfaces and hub surfaces to true condition. As part of the hub surface repairs, FMW also identified a crack in one wheel center casting. This was repaired using industry-standard repair practices, including grinding out the crack and re-building with weldment and proper peening to de-stress the repair.

FMW then turned to quartering the crankpins. Employing a specialized crankpin quartering machine, FMW’s Meador machined the crankpins to in-quarter and stroke tolerances. Since steam locomotive crankpins are set one quarter turn (90 degrees) apart from one side of a locomotive to the other, it is critical to ensure that these pins are precisely 90 degrees apart - wear and tear can result in the engine working its way out of quarter and stroke. Employing the quartering machine, FMW returned each wheelset from WM 1309 to tolerance.

Once all of the machining was completed, FMW protected all machined surfaces with rust inhibitor and wood protective covering prior to arranging and handling the shipping of all six wheelsets to the WMSR shop complex in Ridgely, West Virginia.

Boiler Engineering and 3D CAD Work For Locomotive Rebuild
T1_Trust_1.jpg

FMW VP – Engineering Wolf Fengler, MSME, has been responsible for undertaking Form 4 calculations of some of the largest steam locomotives operating in the preservation era. He was approached by the Pennsylvania Railroad T1 Steam Locomotive Trust in 2016 with the opportunity to be the lead designer of the engineering team associated with building the new boiler for the 4-4-4-4 Duplex locomotive, which is the largest new-build locomotive boiler project undertaken since the end of the steam era.

Fengler began work by re-engineering the boiler barrel for fabrication using modern welding techniques (the original design was of riveted steel construction). This included parallel iterative efforts studying original blueprints, creating 3D CAD models of boiler components in SolidWorks, and calculating stresses per ASME and FRA requirements. Once the design of components were satisfactory, he produced construction drawings from which a selected boiler contractor could begin work.

Of particular importance as it pertains to PRR boilers is the design and fabrication of the Belpaire firebox, including the inner and outer knuckles and the thickness of the sheets themselves. The “Form 4” calculation, as it is referred, requires that the boiler be designed with at least a safety factor of four. Original PRR designs did provide for such a factor of safety, but often it was with a very small margin for corrosion. The design work undertaken for the PRR T1 Trust included verification and modification to the original design to improve the factor of safety and, thus, longevity of the boiler. Staged fabrication work on the cylindrical barrel courses commenced in early 2018.

T1_Trust_2.jpg
Both images courtesy: T1 Preservation Trust

Both images courtesy: T1 Preservation Trust

Locomotive Bearing Box, Crankpin, and Wheel Work on U.S. Sugar No. 148
148_Wheels.jpg

FMW was retained to oversee a variety of detailed engineering and fabrication tasks associated with the driving wheels and driving boxes of U.S. Sugar (USS) steam locomotive No. 148 (No. 148). Originally built for the Florida East Coast Railway in 1920, the light 4-6-2 type locomotive is in the midst of an extensive overhaul to operation for use by USS on its Florida sugar plantation railroad. In particular, FMW was tasked with: 1) wheelset work; 2) crankpin work; and 3) driving box work.

Wheel_Lathe_1.jpg

Wheelset Work | FMW’s Shane Meador began its wheelset work with a detailed inspection of each wheel center, including removing the original tires, sandblasting, and dye penetrant testing the wheel centers. This revealed the wheel centers to have cracks from years of use. Employing railroad standard practice from the era, FMW ground out the cracks and weld-repaired the wheel centers. Then, FMW employed a specialty wheel and journal lathe to re-profile the wheel centers, re-profile the journals, and roll burnish the journals to harden the surfaces. Once this work was completed, Meador ordered and installed new tires for all three wheelsets.

Crankpin-1_sm.jpg

Crankpin Work | FMW burned out the crank pins from each of the wheel centers and undertook quartering of the crank pin bores. This work, as per industry practice, was done after the new tires had been applied to the wheel centers to ensure that the quartering of the bores and pins would not be impacted by the flex associated with the application of new tires. Then, using the original pins as a guide, FMW’s Fengler created new 3D CAD drawings of each of the crank pins. These drawings were used to rough CNC-machine new pins which, after their delivery, were finish machined by Meador to-fit. Finally, once all of the quartering boring and crankpins were completed, Meador used liquid nitrogen to shrink the pins so that they could be inserted into the bores, by hand.

Comparison_SM.jpg

Driving Box Work | FMW was initially tasked with undertaking an inspection of the existing driving boxes on No. 148. The original boxes were found to be quite worn, thus it was determined that manufacturing new driving boxes would be a better cost benefit than repairing the worn out components that came with the locomotive, and it instructed FMW to undertake that work. FMW reverse-engineered the existing boxes, creating 3D CAD drawings, one each for the main and other than main boxes. As part of this process, FMW took into consideration the request to convert the locomotive from “grease cake” lubrication to a force feed lubrication, as was commonplace with the Southern Pacific Railroad. This force feed oil system was also undertaken by Meador on Southern Railway Nos. 630 and 4501, and it has proven reliable over tens of thousands of miles of operation. This system is also used by SP 4449 which, too, has proven quite reliable on the road.

Once each box design was approved, FMW acquired the raw material (a 12 inch thick slab of steel) and began fabrication. Employing a combination of CNC machining and manual machining, FMW: 1) rough machined the boxes; 2) detail machined the boxes; 3) machined and press-fit new crown brasses and hub liners; 4) applied Babbitt to the journal bearing surface; 5) machined the babbitt to-fit; 6) machined all required lubrication paths on the boxes; and 7) finish machined the wedge/shoe surfaces and spreader plates.

Steam Locomotive Cast Iron Weld Repair
Blast_Stand_5.jpg

Our clients are often surprised to hear that broken cast iron castings can be repaired by weldment - but with proper material selection and preparation, FMW has honed a process that can effectively repair cast iron pieces. As a point in case, FMW was recently hired to perform repairs to a large cast iron steam locomotive blast stand.

The cracked assembly was shipped to FMW’s welding facility in Chattanooga, Tenn. FMW oversaw and completed the repair. Our time-honored process melds the combination of proper welding electrode selection with proper material heat treatment. The repair work FMW oversaw saved our client significant time and expense, saving the need to fabricate, or cast, a replacement blast stand.

Blast_Stand_1.jpg
Blast_Stand_3.jpg
Blast_Stand_4.jpg